
DMRyan wrote:I've noticed it's all about the light this bridge is viewed in. When it's bright and sunny, I see the ivory/white color. When it's cloudy or the parts of the bridge are shaded, it looks metallic gray.
dsmLA wrote:I was downtown for lunch (rarity anymore) and noticed they have both sides of the arc in place. This bridge is going to be striking when it is completed.
It will be white instead of blue, with one higher arch instead of two, and not just one, but three walkways.
You'll be able to see the river below with colored lights shining on the bridge," said Cramer.
"You're starting to see the arch come into place, worked on the third our to five. Next week it'll be done," said Cramer.




Ingersoll1978 wrote:Pics from the Asian Botanical Gardens looking towards the new Pedestrian Bridge and Downtown. This view is going to be one of my favorites...wow! These were taken last week...
dogbo wrote:Ingersoll1978 wrote:Pics from the Asian Botanical Gardens looking towards the new Pedestrian Bridge and Downtown. This view is going to be one of my favorites...wow! These were taken last week...
Interesting. I didn't know they had the "waterfalls" now working at the Asian Gardens. That said, the renderings showed the water going directly into the river. That doesn't appear to be how it is working right now. Is this finally a completed project?

dogbo wrote:* why isn't anything else currently happening with the Riverwalk this summer? Soon we'll have the bridge, but still huge gaps in connectivity. Sometime this process reminds me of the person you know that isn't able to multi-task.

DMRyan wrote:Sounds like most of the remainder of the west bank riverwalk projects will have to go out for bid again due to an oversight in trying coordinate bureaucratic requirements with both the IDNR and Corps of Engineers.
DMRyan wrote:Sounds like most of the remainder of the west bank riverwalk projects will have to go out for bid again due to an oversight in trying coordinate bureaucratic requirements with both the IDNR and Corps of Engineers.
Des Moines Riverwalk. The Corps of Engineers has prepared an Engineering Documentation Report for the project and is preparing Plans and Specifications. The first Federal construction contract is scheduled for late 2008.
Return to Downtown Development
Users browsing this forum: dogbo and 0 guests